§ 13.12.0421. Schedule NP-03—Nonprofit—Time of use rate.  


Latest version.
  • A.

    Applicability. This schedule applies to all nonprofit tax-deductible organizations.

    B.

    Character of service. Sixty cycle, alternating current at such phase and voltage as the City may have available will be furnished under this schedule, applied through a single meter and one point of delivery.

    C.

    Time of use rate effective January 1, 2018:

    1.

    Base charge.

    a.

    Single phase $24.90 per month.

    b.

    Three phase $62.23 per month.

    2.

    Energy usage charge between June 1 and August 31, shall be $0.1131 per kWh during heavy load hours, $0.1131 per kWh during medium load hours, and $0.0422 per kWh during light load hours.

    3.

    Energy usage charge between September 1 and May 31, shall be $0.1248 per kWh during heavy load hours, $0.1248 per kWh during medium load hours, and $0.0383 per kWh during light load hours.

(Ord. 3601 § 1, 12/19/2017; Ord. 3539 § 1, 9/1/2015; Ord. 3513 § 1, 10/7/2014; Ord. 3489 § 1, 11/5/2013; Ord. 3464 § 1, 10/16/2012, eff. 1/7/2013; Ord. 3452 § 1, 4/17/2012)