§ 13.12.044. Schedule GD-04—General service demand—Primary metered—Time of use rate.  


Latest version.
  • A.

    Applicability. This schedule applies to all accounts not covered by other rate schedules with the following types of service:

    1.

    120/208 or 120/240 volts, single or three phase, service panel larger than 400 amps.

    2.

    240/480 or 277/480 volts, three phase service panel larger than 200 amps.

    3.

    When electric current is measured at primary voltage and delivery to the customer is at secondary voltage.

    B.

    Character of service. Sixty cycle, alternating current at such phase and voltage as the City may have available will be furnished under this schedule, applied through a single meter and one point of delivery.

    C.

    Time of use rate effective January 1, 2018:

    1.

    Base charge:

    a.

    Single phase $49.45 per month.

    b.

    Three phase $132.30 per month.

    2.

    Monthly energy charge between June 1 and August 31, shall be $0.0683 per kWh during heavy load hours, $0.0683 per kWh during medium load hours, and $0.0255 per kWh during light load hours.

    3.

    Monthly energy charge between September 1 and May 31, shall be $0.0683 per kWh during heavy load hours, $0.0683 per kWh during medium load hours, and $0.0231 per kWh during light load hours.

    4.

    Billing demand:

    a.

    Billing demand for each month shall be based on the maximum hour of kVA (apparent power) during heavy and medium load hours.

    b.

    Demand usage charge: $5.20 per kVA.

(Ord. 3601 § 1, 12/19/2017; Ord. 3539 § 1, 9/1/2015; Ord. 3489 § 1, 11/5/2013; Ord. No. 3464 § 1, 10/16/2012, eff. 1/7/2013; Ord. No. 3452 § 1, 4/17/2012)