§ 17.44.240. Final approval of PLID.  


Latest version.
  • Application for final approval of a PLID shall be submitted to the Community and Economic Development Department within two years of the preliminary development plan approval; provided that, for phased PLID's each phase shall have an additional one-year period for final approval; and provided further, that an applicant may apply to the Community and Economic Development Department, for one or more one-year extensions as the department may deem appropriate. The site must be under one ownership prior to final approval by the Hearing Examiner. The application for final approval must be made by the owners of the entire site and shall include the following:

    A.

    A title report showing record ownership of the parcel or parcels upon which the PLID is to be developed.

    B.

    Adequate assurance for the retention and continued maintenance of stormwater management facilities, common open space, recreation facilities, and recreation structures. If development is to be done in phases, each phase must meet this requirement.

    C.

    Adequate assurance for the retention and continued maintenance of environmentally sensitive areas and their buffers. If development is to be done in phases, each phase must meet this requirement.

    D.

    Final development plans that shall be in compliance with the approved preliminary development plans.

    E.

    Final corrected plans ("as-builts") that are stamped, signed, and dated by a licensed engineer registered in the State of Washington that accurately represent the stormwater infrastructure installed including bioretention facilities, permeable pavement, vegetated roofs, rainwater harvesting systems, and/or newly planted or retained trees for which a flow reduction credit was received.

    F.

    The final plat, if applicable, pursuant to Chapter 58.17 RCW and Chapter 16.08 PAMC.

    G.

    Development schedule.

    H.

    If bonding is proposed, the bond or other form of security acceptable to the City in an amount equal to 150 percent of the approved engineering estimate for the required improvements to complete the project or submitted phase, as required by the City.

    I.

    Covenants, conditions and restrictions and/or homeowners' association agreement.

    J.

    Mailing labels of property owners within 300 feet of the proposed project pursuant to section 17.96.140 PAMC.

(Ord. 3572 § 21, 12/20/2016; Ord. 3548 § 21, 1/5/2016; Ord. 3517 § 6, 10/21/2014; Ord. 3293, 8/31/2007)